Assess equipment FAT/delivery status and track licensing preparation progress.
Preparation of Energization procedure, define SAT/energization management objectives.
Develop an equipment list for monitoring construction progress of key devices (SWGR/MCC/TR/Busduct, etc.).
Compile a list of managed electrical equipment.
Define and enter the level of construction item management.
Manage SAT schedule/Vendor SV manpower utilization/test equipment operation, etc.
Review/adapt test items from the standard SAT list according to project traits, and specify test subjects (R&R) considering the capabilities of the testing specialist company and regional features.
Confirm SAT procedures, including equipment-specific ones.